Scope a BACnet metering retrofit by checking the meter suffix, firmware, communications module and one measured value before ordering equipment.

For a switchboard retrofit, ask the site team for the meter schedule, the communications option fitted to each meter and the firmware shown by the commissioning software. A photograph of the front panel can identify the family while leaving the Ethernet module hidden. If the building controller already collects these meters, ask whether it can share the required readings before allowing for new meter connections.

Decide what each board needs

  • Accuenergy Acuvim II or L. The Acuvim IIR and IIW and Acuvim CL and EL can use an AXM-WEB2 module for BACnet/IP. Check whether that module is fitted and whether the service is enabled. A meter already on a BACnet MS/TP trunk may be reachable through the building’s existing router. Record which route serves each board.
  • Accuenergy Acuvim 3. The Acuvim 3 has Ethernet on the meter. For a building that also exports electricity, allow for two energy counters. Its BACnet object list assigns AI 2056 to imported active energy and AI 2064 to exported active energy, both in kWh. Confirm direction and compare the change in each counter over the same reporting interval.
  • Carlo Gavazzi WM20, WM30 and WM40. Photograph the communications module on the rear of the WM analyser. MCBACIP exposes readings over Ethernet. With MCBACMS, identify the BACnet router serving the serial trunk before allowing for new hardware. Its Ethernet port is for configuration.
  • Crompton Integra 1630. Read the communications option on the rear label before quoting network work. The Integra 1630 guide distinguishes the 080 BACnet/IP card from the 070 Modbus TCP card and the 090 serial BACnet card. For option 090, include the existing MS/TP router or allow for one in the scope.
  • Schneider Electric PowerLogic PM5560. The PM5560 guide identifies the BACnet/IP option from firmware 2.3.0. Record the installed version and Ethernet route. An existing serial Modbus installation can also be useful when the required outcome is an energy trend.
  • Schneider Electric PowerLogic PM8240. The PM8240 guide covers the BACnet/IP server introduced with firmware 4.6.0. Ask the site engineer to check the enabled server and its Device instance in ION Setup.

For a Leviton VerifEye 7000 or 7100, include the element-to-feeder schedule. Two loads on one meter share a Device instance but report power through different BACnet objects. Compare each reading with its own element in the meter software.

For a panel containing Measurlogic meters, use the DTS selection guide to match the object type and units to the fitted BACnet interface.

Choose a serial meter for a new feeder

A building with an existing BACnet MS/TP trunk can use a meter on that trunk through its BACnet router. Check the electrical input before choosing among Schneider’s iEM models.

  • The iEM3165 measures up to 63 A directly. For tenant consumption, compare the imported energy counter in Wh with the panel reading in kWh.
  • The iEM3365 extends direct measurement to 125 A. Confirm the feeder design current and panel requirements before quoting this option.
  • The iEM3265 takes 1 A or 5 A current transformer secondaries. Record the installed CT ratio and compare phase current with the display before collecting energy totals.

For an existing PowerLogic PM5300 panel meter, read the complete suffix. The PM5300 model guide distinguishes the Ethernet PM5320, PM5340 and PM5341 from the serial Modbus variants. Schneider’s support FAQ identifies hardware revision B1 on the meter label. If the asset is an ION9000, check the firmware and enabled BACnet/IP server. On firmware 4.6.0, verify total real power against the display using Analog Input 3060 in kW.

For a Continental Control Systems WattNode retrofit, read the complete order code. The WNC-3D-BN delta guide lists the line-to-line voltages for three-wire services. The WNC-3Y-BN wye guide matches four-wire services by both voltages. For example, the 3Y-400 model corresponds to 230 V phase to neutral and 400 V phase to phase. The BN suffix identifies the BACnet version. Record the output type and primary rating of each CT already on the feeder.

Veris meter suffixes and current inputs

The E50H2 and E50H5 take 0.333 V or 1 V CT inputs. The E50H2A and E50H5A have built-in integrators for E683 rope CTs. Record the fitted CT model before pricing either pair. The H5 versions add local data logging.

For a generation feeder, the E51H2 and E51H5 expose separate import and export totals. Verify the quantity as well as the object number. Analog Input 2 is total active power in kW on the E50H models above and imported energy in kWh on the E51H models.

Decide whether the router stays with the panel

For a survey, the portable BASRTP-B draws power over USB while the commissioning computer communicates over Ethernet. Agree who will provide the permanent connection when the engineer leaves. If the panel needs its own router, the BASRT-B mounts on DIN rail and takes 24 V AC or DC. Check for an existing route before adding either unit to the quote.

Metering the water side of a heating or cooling plant

A feeder meter measures electrical input to the plant. For heat delivered to a water branch, identify the installed calculator: System-10, System-20 or System-40. A D-100 displays flow from a separate meter. Use the flow and heat meter guide to select the reporting unit, identify the network interface and check a reading against the display.

Count feeders on a multi-circuit meter

A single Ethernet connection can carry measurements from several feeders. On a DENT PowerScout HD, identify each metering element as well as the meter. In the standard point list, Analog Input 1167 is the total kW for Element A. On a model with Element B, its total is Analog Input 11167. Check the selected element against the circuit name in ViewPoint HD before multiplying the point schedule across a board. Include the number of occupied elements and the measurements required per element when requesting a quote.

Prove one reading and price the remainder

On an Acuvim II V3 matching the firmware 6.39 point list, Analog Input 2 is phase A voltage in volts. Read Present_Value and Units, then compare the reading with the meter display or the module’s own dashboard. Record the Device instance, phase and time. A line-to-line reading is a different quantity even though both readings are in volts.

For a consumption report, repeat the comparison on the import energy counter and record its unit and direction. A successful voltage comparison establishes the network path. It leaves the energy counter and its scaling to be checked on their own terms.

In the project enquiry, group the boards by connection type. Give the number of reachable Ethernet meters, meters on routed serial trunks and meters needing an additional module or router. Include the number of energy counters per board, collection interval and who will provide access to the controls network.