Flexibility and grid codes

Virtual power plants, peak shaving, demand response, battery storage, frequency response and grid codes.

Grid rules and flexibility markets decide what a site must measure, how fast, and who receives the data.

Start with what a virtual power plant is, then read the rules for your country: G99 in Great Britain or Section 14a in Germany.

Flexibility

13 guides · about 159 minutes

  1. What is a virtual power plant? A virtual power plant (VPP) pools batteries, generators and flexible loads on many sites into one unit an aggregator dispatches. How it works and what it sells. 13 min
  2. What is demand side response (DSR)? Services, payments and measurement Demand side response pays a site to change its electricity use when the grid needs it. The GB, Irish and EU routes, which loads can flex, and how delivery is measured. 14 min
  3. What is peak shaving? Peak shaving vs load shifting Peak shaving cuts the highest interval demand; load shifting moves kWh to cheaper hours. Demand charges, demand response, load levelling and a battery example. 16 min
  4. EVs as grid assets: V1G, V2G, V2H and V2B V1G, V2G, vehicle-to-home and building: power levels, standards, connection rules, a worked headroom example and site measurement needs. 8 min
  5. OCPP for EV charging networks OCPP is the open protocol between EV chargers and their management system. OCPP 1.6 vs 2.0.1 vs 2.1, security profiles, charging profiles and fallback limits. 11 min
  6. What is dynamic load management for EV charging? Dynamic load management shares a site's spare connection capacity between EV chargers. Static vs dynamic, the 6 A floor, phases, fallbacks and a worked example. 11 min
  7. IoT in demand response: signals, control and verification How a site receives a demand response instruction, changes its load safely and proves what it delivered, and what metering and control each step needs. 12 min
  8. Demand response baselines and measurement Measure demand response: DFS P376 and self-nominated baselines, capped same-day adjustment, baseline accuracy and evidence of delivery. 12 min
  9. What is dynamic response? Dynamic frequency response explained Dynamic response changes power continuously with grid frequency. NESO's Dynamic Containment, Moderation and Regulation compared, and the DC curve for a battery. 14 min
  10. What is FCAS? Australian frequency services and measurement FCAS are the reserves AEMO buys to hold NEM frequency near 50 Hz. The ten FCAS markets, how they are paid, MASS measurement rules, sign conventions and droop. 16 min
  11. BESS control: BMS, EMS and PCS explained In a BESS the BMS protects the cells, the PCS converts DC to AC and the EMS decides when to charge and discharge. Who owns each limit, and the data to read. 11 min
  12. BESS control: verify commands and the asset response Verify battery commands from request to metered response: clock synchronisation, a 500 kW example, expiry handling and commissioning tests. 11 min
  13. Local control: interlocks and a failure matrix Plan local gateway control: authority, interlocks, lost links, stale data, timeouts, restarts and tests before enabling automation. 10 min

Grid connection rules

9 guides · about 115 minutes

  1. UK G99 grid connection requirements G99 covers GB generation and storage above 16 A per phase: Types A to D, the DNO application process, protection settings, storage rules and G100 export limits. 15 min
  2. Ireland RESS 6: project monitoring and auction dates Current RESS 6 auction dates, the roles of metering and operational monitoring, and a practical evidence plan for Irish wind, solar and hybrid projects. 7 min
  3. Spain: independent aggregation and demand response What Royal Decree 88/2026 changes for independent aggregation in Spain, which implementation steps still matter, and the site data needed for demand response. 7 min
  4. France NEBCO: demand flexibility and load shifting How France's NEBCO rules value demand reduction, anticipation and deferred consumption, and the metering, baseline and control records a flexible site needs. 9 min
  5. Section 14a EnWG: controllable devices and network charges §14a EnWG since 2024: new heat pumps, wallboxes and batteries over 4.2 kW accept DSO control, never below 4.2 kW. Modules 1 to 3 and the control box. 13 min
  6. VDE-AR-N 4110: medium-voltage connection rules explained VDE-AR-N 4110:2023-09 is the German medium-voltage connection rule: scope, 4105 or 4110, unit and plant certificates, reactive power and commissioning. 14 min
  7. Dutch Realtime Interface (RTI) for generation above 1 MW Dutch RTI connections: customer endpoint duties, setpoints, lost-link behaviour and the boundary with plant control and site monitoring. 11 min
  8. Renewable energy grid integration and stability How solar and wind affect grid stability: voltage rise, inertia and RoCoF, system strength, ride-through, the fix for each, and GB, Irish and Australian events. 21 min
  9. What is a microgrid? Components, types and control A microgrid is a local group of loads, generation and storage that runs with the grid or as an island. Its components, types and controller, and how it islands. 18 min

More in Flexibility and grid codes

Calculators

All calculators

EpiSensor products

Preparing a site for a flexibility service?

Tell System Builder which assets you want to control or measure. It maps them to demand response and metering hardware.

Build a system