Flexibility and grid codes

VDE-AR-N 4105: current edition, key requirements and monitoring

VDE-AR-N 4105:2026-03 is the current edition, published 27 February 2026: scope, the 800 VA and 30 kVA limits, NA protection settings and changes from 2018.

VDE-AR-N 4105 is the VDE FNN technical connection rule for generation plants and storage connected to the German low-voltage network. It sets the minimum technical requirements for their connection and their parallel operation with the distribution system operator's (DSO's) network: the connection process, connection design, plant behaviour, network and plant protection (Netz- und Anlagenschutz, NA protection), billing metering, operation and the evidence of electrical characteristics. The current version is VDE-AR-N 4105:2026-03, published on 27 February 2026.

VDE-AR-N 4105 at a glance

TopicVDE-AR-N 4105:2026-03
Current editionVDE-AR-N 4105:2026-03, published by VDE FNN on 27 February 2026. It replaces VDE-AR-N 4105:2018-11 and Berichtigung 1:2020-10
Applies toAll generation plants and storage operated in parallel with the DSO's low-voltage network, including systems that do not export, and extensions or changes of existing plants
Simplified connection process (section 4.4)Total inverter apparent power S_Amax of 800 VA or less, including DC-coupled generation and storage units. Above 800 VA, the registration procedure of section 4.2
Plug-in solar devicesUp to 2 kWp may be put into operation without an electrician (DIN VDE V 0126-95). All other plants and storage need an electrical contractor
Central NA protection (section 6.1)Required when the total inverter apparent power ∑S_Amax exceeds 30 kVA
Reactive powerQ(U) is the standard method as delivered. The DSO may set a cos φ(P) characteristic or a fixed cos φ instead
60% PV limit of EEG section 9Until 1 March 2028, by certified P_AV,E protection to the 2026 edition, certified P_AV,E monitoring to the 2018 edition, or a permanent active power reduction at the inverter (section 5.7.1)
Medium-voltage connectionCommissioning form F.9 covers plants on the DSO's medium-voltage network with ∑P_Amax from 135 kW to 500 kW and P_AV,E up to 270 kW, set with a medium-voltage parameter set
FormsAnnex F: F.1 application to F.11 operating permit procedure, published free of charge by VDE FNN

Sources: VDE FNN public page and FAQ for VDE-AR-N 4105:2026-03, the VDE Verlag scope summary and the Annex F forms. The full rule is sold by VDE Verlag, and the responsible DSO's TAB apply with it.

NA protection settings

Form F.6, the requirements for the NA protection test report, lists the setting values that the protection must be tested at:

Protection functionInverters, fuel cells and generators up to 50 kWDirectly coupled synchronous and asynchronous generators above 50 kW
Overvoltage U>>1.15 × Un1.25 × Un
Overvoltage U>, 10-minute moving mean1.10 × Un1.10 × Un
Undervoltage U<0.8 × Un0.8 × Un
Undervoltage U<<Not used0.45 × Un
Underfrequency f<47.5 Hz47.5 Hz
Overfrequency f>51.5 Hz51.5 Hz
Overfrequency f>>52.6 Hz52.6 Hz

The trip time runs from the moment the voltage or frequency limit is crossed to the trip signal at the coupling switch. The disconnection time, the trip time plus the operating time of the coupling switch, must not exceed 200 ms for U>> and f>>. The trip times of each function are in the rule and on the protection certificate. A monitoring system that records the same voltage does not test or replace this protection.

What changed from the 2018 edition

The VDE Verlag summary lists twelve changes from VDE-AR-N 4105:2018-11. The main ones:

  1. A simplified connection process and simplified minimum requirements for plants and storage up to 800 VA.
  2. Further development of P_AV,E monitoring into a P_AV,E protection function, and rules for zero export.
  3. Q(U) as the standard reactive power method as delivered.
  4. Stricter system-support requirements, such as RoCoF, P(f) and the NA protection settings, and new NA protection variants.
  5. Requirements and verification for bidirectional charging equipment.
  6. A connection and verification process for plants up to set power limits that connect at a higher voltage level.
  7. A plant certificate above set power thresholds, revised connection forms with fewer data fields, FAQ content taken into the rule and updated meter panel examples.

For an existing, unchanged part of an installation, the summary states no obligation to adapt, provided a safe and undisturbed supply is ensured.

Transition from the 2018 edition

VDE FNN lists VDE-AR-N 4105:2026-03 as in force. The public VDE material does not provide one broad transition rule covering every plant already planned, ordered, commissioned or modified under VDE-AR-N 4105:2018-11. Do not infer that every existing plant must be rebuilt immediately, or that every unfinished project may continue under the old edition. Record the design date, application date, equipment certificates, connection offer and planned commissioning date, then ask the responsible DSO to confirm the applicable edition and transition treatment.

The FAQ on the Solarspitzengesetz 60% PV-module limit permits the three routes in the table until 1 March 2028. That is a provision for that function, not a general transition period for the whole rule.

Monitoring is not the connection evidence

A solar, battery or generator dashboard may show exactly what happens behind a German low-voltage connection. It does not show which technical rule the DSO accepted, whether the protection scheme is certified or whether parallel operation has been commissioned. A monitoring project must therefore begin with the approved connection concept. A local meter may explain plant behaviour, but it does not define which edition applies, approve an inverter, prove protection operation or authorise parallel operation.

Separate the rule from the law and the DSO conditions

VDE-AR-N 4105 is an application rule, not legislation. EnWG section 19 requires electricity network operators to publish technical connection conditions. It also provides the framework for national general technical minimum requirements and for clearly identified DSO-specific additions or choices.

EnWG section 49 requires energy installations to be built and operated with technical safety and states that compliance with recognised engineering practice is presumed when the VDE technical rules for electricity are followed. For renewable generation, EEG section 10 separately requires the connection and safety equipment to meet the DSO's necessary technical requirements and EnWG section 49.

For a real project, read together:

  1. the current VDE-AR-N 4105 edition;
  2. VDE-AR-N 4100 for the low-voltage customer installation;
  3. the responsible DSO's published Technische Anschlussbedingungen (TAB) and stated settings;
  4. the connection offer and project-specific correspondence; and
  5. the applicable statutory registration, connection and metering duties.

A generic monitoring specification cannot override any of these documents.

Confirm that the plant is actually in scope

The public VDE Verlag scope summary says the 2026 rule applies to all generation plants and storage operated in parallel with the DSO network. This includes systems that do not export and extensions or changes to existing plants. A zero-export setting therefore does not by itself turn a grid-parallel inverter into an island system or remove the connection process.

The voltage level also matters. VDE-AR-N 4105 is the low-voltage rule. A project connected at medium voltage normally falls under VDE-AR-N 4110 even when individual inverters or meters use low-voltage interfaces. The 2026 edition adds a 4105 process for some smaller plants at a higher voltage level: its commissioning form covers medium-voltage connections with ∑P_Amax from 135 kW to 500 kW and P_AV,E up to 270 kW. Confirm the point of connection and the DSO's classification before selecting equipment or evidence.

Keep certified connection evidence intact

The freely published Annex F forms show the connection evidence expected by the process. The application form requests, where applicable, ZEREZ identifiers for unit certificates, the NA-protection certificate and optional power-flow-monitoring protection, plus a single-line diagram. Other forms cover plant data and commissioning.

VDE FNN's public FAQ states that the sum of maximum apparent powers of all inverters, ∑S_Amax, determines whether central NA protection is required; when it exceeds 30 kVA, central NA protection is required. Its example is a 25 kWp PV array with 33 kVA of inverters, which needs one. It also warns that a permanent software reduction used in that assessment must be declared, protected against unauthorised reversal and remain effective through software updates.

Treat these as formal evidence paths. Preserve the approved single-line diagram, certificate identifiers, protection settings, coupling-device design, test results, commissioning declarations and DSO acceptance. A dashboard screenshot, Modbus register read or cloud alarm is not a substitute.

Design owner monitoring as a separate layer

Owner monitoring can still be valuable. Place measurements at boundaries that answer operational questions:

BoundaryOwner questionBoundary of the evidence
Grid connection pointIs the site importing, exporting or approaching its agreed limit?Does not replace the DSO or billing meter
Generation feederWhat active and reactive power is the plant producing?Does not prove certified inverter behaviour
Storage feederIs the battery charging or discharging within the operating plan?Does not replace battery protection or certified control
Major site loadsIs local demand causing an apparent export-control error?Does not alter the approved connection concept

Record timestamps, phase values, active and reactive power, sign convention, data quality, device status and communication gaps. Keep missing data missing; do not turn a lost connection into zero generation.

Where an export controller or P_AV,E function is part of the approved scheme, use only the certified architecture and settings accepted for that project. A separate EpiSensor meter may provide comparison and diagnostics, but it must not become a second writer competing for the inverter set point or claim the protection function.

Define commissioning and change control

Before parallel operation, reconcile the installed equipment against the approved documents. Capture certificate IDs, firmware or parameter set where required, protection settings, test records, meter identities and the signed commissioning documents. Keep the DSO's approval and any operating restrictions with the site record.

Apply the same discipline to later changes. Adding storage, replacing an inverter, changing maximum apparent power, changing export limitation or updating control firmware may affect the approved design. Ask the installer and DSO whether a new application, evidence update or recommissioning is required before making the change.

Where EpiSensor fits

EpiSensor can provide owner-side interval measurements, equipment status, alarms and approved integrations around PV, generators and storage. A Gateway running Edge can retain timestamped operational data on site and forward approved records to the owner's platform.

This layer does not certify an inverter or NA protection, perform the electrician's tests, issue a ZEREZ identifier, approve the single-line diagram, commission the grid connection, replace the billing meter or act as the DSO's mandated control channel. System Builder can help define operational measurement after the connection point, applicable rule, DSO requirements and certified protection design are fixed.

Common questions

Which version of VDE-AR-N 4105 is current?

VDE FNN lists VDE-AR-N 4105:2026-03 as in force, published on 27 February 2026. The public page does not state a general migration rule for every project already designed, ordered or connected under the 2018 edition. Confirm the applicable edition and any transition treatment with the responsible DSO in writing.

What does VDE-AR-N 4105 cover?

The minimum technical requirements for connecting generation plants and storage to the German low-voltage network and operating them in parallel with it: the connection process, connection design, plant behaviour such as reactive power and frequency response, network and plant protection (NA protection), billing metering, operation, the evidence of electrical characteristics and temporarily connected plants.

When is a central NA protection required?

When the sum of the maximum apparent powers of all inverters, ∑S_Amax, exceeds 30 kVA. VDE FNN's FAQ gives the example of a 25 kWp PV array on 33 kVA of inverters, which needs central NA protection. A permanent software reduction of S_Emax can lower ∑S_Amax, if it is documented, protected against change and kept through software updates.

What is the 800 VA rule in VDE-AR-N 4105?

Section 4.4 of the 2026 edition gives a simplified connection process for very small generation plants and storage, including DC-coupled generation and storage units, with a total inverter apparent power S_Amax of 800 VA or less. They are notified on form F.1.2. Above 800 VA, the standard registration procedure of section 4.2 applies. Plug-in solar devices up to 2 kWp may be put into operation without an electrician under DIN VDE V 0126-95; every other plant needs a registered electrical contractor.

Which forms does the DSO need under VDE-AR-N 4105?

Annex F holds them: F.1 application, F.2 datasheet, F.3 unit certificate, F.5 NA protection certificate, F.7 P_AV,E protection certificate, F.8 plant certificate, F.9 commissioning record, F.10 declaration of conformity and F.11 operating permit procedure. For PV up to 30 kWp and for storage, the data fields of the FNN note on standardised registration apply in the DSO's portal. Which forms a project needs depends on its size and design.

Is VDE-AR-N 4105 German law?

It is a VDE application rule containing technical minimum requirements. The statutory framework is separate. EnWG section 19 requires electricity network operators to publish technical connection conditions, while section 49 requires technical safety and creates a presumption for compliance with recognised engineering practice when VDE technical rules are followed.

Does zero export remove VDE-AR-N 4105 from scope?

No. VDE Verlag's public scope summary says the 2026 rule applies to generation plants and storage operated in parallel with the DSO network, including systems that do not export. The approved connection concept and DSO requirements still govern the project.

Can an energy monitor replace NA protection or commissioning tests?

No. Owner monitoring is a separate operational layer. It cannot become the certified Netz- und Anlagenschutz, coupling device, unit certificate, protection test, commissioning declaration or DSO acceptance merely by measuring the same voltage or power.

What can EpiSensor contribute?

EpiSensor can provide separate owner-side interval measurements, alarms and approved equipment integration. It cannot certify VDE-AR-N 4105 compliance, commission the grid connection, operate as the DSO's mandated control path or replace approved settlement metering and protection.