Demand-response event energy and rebound worksheet

Compare event and rebound power with their baselines interval by interval, and with the committed reduction.

Calculate

Event series
minutes
kW
Enter one time-ordered baseline kW value per event interval.
Enter one time-ordered actual kW value per event interval.
Post-event rebound series
Enter one baseline kW value per post-event interval.
Enter one actual kW value per post-event interval.

Worked example

Event energy reduction

 kWh

Average event reduction
 kW
Average reduction against commitment
 %
Post-event actual minus baseline (signed)
20 kWh
Reduction after rebound
86.25 kWh
Intervals below the commitment
intervals

Positive import and negative export are assumed. A positive post-event deviation reduces the net event effect; a negative value means further reduction. Programme baseline, exclusions and settlement rules remain authoritative.

Underlined figures are rounded. Select one to copy its full value.

Method and assumptions

Formula

event energy reduction = Σ(baseline − actual) × interval hours; rebound = Σ(post-event actual − baseline) × interval hours

The baseline method and programme rules determine whether these arithmetic differences are commercially valid.

Limits of this result

  • This worksheet does not establish or approve a settlement baseline; use the programme’s documented methodology.
  • Weather, production, occupancy, schedules and event notification can require baseline adjustment or exclusion.
  • Availability, telemetry quality, command acknowledgement, rebound limits and non-delivery rules remain programme-specific.
  • Every series must contain complete, equally spaced interval-average kW values with shared timestamp boundaries and positive import / negative export.

Technical sources

  1. Measurement and Verification for Demand ResponseUS Department of Energy and Federal Energy Regulatory Commission · Final report, 2013-02
  2. Demand response application guideEpiSensor · current website application record

Put the value to work

Read the related engineering guidance, or carry this task into System Builder to identify the signal path and EpiSensor products.

On this page