Huawei LUNA2000-241-2S1
Commercial and utility battery energy storage system
LUNA2000-241-2S1 combines 241 kWh of LFP storage with a 108 kW PCS, hybrid cooling, Ethernet or fibre and a named Modbus TCP interface. Edge reads it over Modbus TCP, directly or through a SmartLogger3000, using the project point map for the installed firmware.
Compatibility
Compatible with EpiSensor Edge over Modbus TCP
Huawei's datasheet names Modbus TCP over Ethernet or fibre, and Edge is a Modbus TCP client. Edge reads the cabinet on the site network, or the SmartLogger3000 that manages it over the SmartLogger's Modbus TCP interface. The read points come from the project's point map for the installed firmware.
LUNA2000-241-2S1, datasheet version 01-202601 and user manual issue 19. Site check: obtain the point map for the installed firmware and the endpoint in use, the ESS itself or the SmartLogger3000. Keep PCS2000-108K-MB1, pack optimisers, BMS, EMS, meters and project controller identities separate. Read-only monitoring; no control or safety authority is transferred.
Connect it with
When the project exposes the cabinet’s own Modbus TCP endpoint to a monitoring client
- Modbus
- Edge
- Platforms
When the cabinet is managed by a SmartLogger3000
- Wired
- Edge
- Platforms
Models
| Models | Interface | Route into Edge |
|---|---|---|
| LUNA2000-241-2S1 | 241 kWh ESS with PCS2000-108K-MB1, Ethernet, fibre and Modbus TCP | Read over Modbus TCP, directly or through the SmartLogger3000, with the project point map for the installed firmware. |
| LUNA2000-215-2S10 | Separate 215 kWh C&I model on the same support family page | Use its own datasheet and project interface contract; do not transfer 241-2S1 values. |
Specifications
The January 2026 datasheet specifies 241.0 kWh, a 108 kW PCS and four 240S1P LFP packs in one LUNA2000-241-2S1 system.2
- Stored energy
- 241.0 kWh maximum2
- PCS
- PCS2000-108K-MB1, 108 kW nominal output2
- Battery
- LFP, 314 Ah cells, four 240S1P packs2
- Published communications
- Ethernet, fibre and Modbus TCP2
- Environment
- IP55; -30 to +55 °C, derating above +50 °C; up to 4,000 m2
- Safety scope
- Fire, anti-islanding, insulation, residual-current and overcurrent functions remain with the commissioned system2
Interface
Documented measurements and integration boundaries for LUNA2000-241-2S1.
- Potential identity, operating mode, state of charge, state of health, power, energy, temperatures and alarms require the approved project point map.
- Pack optimiser, battery, PCS, EMS, site-meter and grid-meter values must retain their distinct sources and time bases.
- Fire-system, anti-islanding, insulation, residual-current and overcurrent functions remain under the commissioned safety and protection design.
- No power setpoint, charge, discharge, grid-forming, anti-backflow, black-start or protection command is approved by this guide.
Assessment
LUNA2000-241-2S1, datasheet version 01-202601. Edge reads it over Modbus TCP, directly or through the SmartLogger3000. Keep PCS2000-108K-MB1, pack optimisers, BMS, EMS, meters and project controller identities separate. No control or safety authority is transferred.
- InteroperabilityLimited
- The manufacturer names relevant communications, but the retained public evidence does not provide a complete firmware-matched, read-only third-party interface contract.12
- AccuracyNot yet assessed
- The public datasheet does not list the readable point set, units, sign conventions, quality states or freshness rules; they come from the project point map.12
- SecurityNot yet assessed
- Authentication, encryption, roles and read-only privilege separation for an independent client are not defined in the retained public sources.12
- ReliabilityLimited
- System operating limits are published; client recovery, stale-data behaviour and concurrent-client limits are set by the project configuration.12
- RuggednessSupported with conditions
- IP55, temperature, humidity and altitude limits are published; the installed site and fire design remain authoritative.12
Setup
-
Confirm the delivered system
Record every enclosure, battery rack, PCS, BMS, EMS, meter and controller identity, plus firmware, software, network and contract revisions.
-
Map authority before data
Document which system owns charge and discharge, protection, fire and life safety, grid control, market dispatch, settlement, warranty and emergency response.
-
Obtain the interface contract
Use user manual issue 19, section 9.4, to record the actual network arrangement. DHCP is enabled by default. For multiple cabinets using static addresses, configure each ESS consistently and record a unique address through the local app’s Communication settings and Wired Network Settings. Select the matching SmartLogger3000 or SmartLogger5000/SmartMGC5000 solution manual for the site topology.
-
Prove read-only monitoring
On SmartLogger3000, open Monitoring, ESS, Running Info and Basic Information to confirm the selected cabinet identity. Keep startup authorization with the commissioning provider: the manual requires a vendor or authorized service provider for the startup code. Compare the cabinet’s reported operating state and power with the site meter during a known interval; request the external read map for the chosen controller instead of tapping internal BCU or PCS links.
Common questions
- Is the LUNA2000-241-2S1 compatible with Edge?
- Yes, over Modbus TCP: Edge reads the cabinet or the SmartLogger3000 that manages it on the site network. The public datasheet does not publish addresses, types, units or permissions, so take those from the project point map for the installed firmware.2
- Can the 215 kWh model use this guide?
- No. LUNA2000-215-2S10 has a different capacity and battery configuration. Use its exact datasheet and project contract.1
- Can Edge control anti-backflow or grid-forming operation?
- No. Those functions depend on the project EMS, meters, protection and grid approval. This guide releases no write path.2
Sources
- LUNA2000-241 Series support page (opens in a new tab)
- LUNA2000-241-2S1 datasheet, version 01-202601 (opens in a new tab) (PDF)
- LUNA2000-(107-241) series user manual, issue 19, 5 September 2026 (opens in a new tab)
Further reading
- ApplicationBattery demand response
- GuideBESS, BMS, EMS and PCS roles
- ToolBattery autonomy calculator
- ToolModbus register address converter
- ToolModbus data decoder
- ToolRS-485 termination and bias
- GuideModbus RS-485 commissioning
- ManufacturerHuawei devices
- ProtocolModbus devices and register maps
- CategoryBattery systems and controls
Product names and trademarks belong to their owners. Publication does not imply endorsement or a commercial relationship.