A plant schedule may identify a rooftop unit by its cooling capacity and location. To quote BACnet monitoring, the controls contractor also needs the unit controller, fitted communication interface and route from the equipment panel to the building network.
Match the interface to the equipment
| Equipment on site | Interface | Example to check |
|---|---|---|
| Chiller with CH530 controls | Trane BCI-C | Compare actual leaving-water temperature with the chiller display. Keep the active setpoint as a separate point. |
| IntelliPak rooftop or commercial self-contained unit | Trane BCI-I | Identify the temperature sensor and operating mode for the air system served by that unit. |
| ReliaTel rooftop unit | Trane BCI-R | Look for discharge-air temperature. Check the unit options before promising humidity or duct pressure trends. |
Identify a unit controller
On a variable-air-volume box, the UC210 and UC400 can expose terminal airflow. Ask for the balancing record for that specific box. The UC400 can also run a custom program, so its model number alone cannot identify the available measurements.
For a UC600 air handler, check the firmware and active network. Version 5.0 and later can use BACnet/IP over Ethernet. For a CenTraVac chiller with a UC800, use the evaporator status display to distinguish measured leaving-water temperature from the active setpoint.
Estimate repeated work
Ask for a dated point list from each distinct equipment configuration. Two rooftops with the same interface may have different sensors. For an estate of ten units, group them by unit family, options and controller software first. A verified mapping for one configuration gives the estimator a basis for pricing its repeats.
At one representative unit, record the BACnet Device instance, object identifier, unit and simultaneous local reading. Confirm which BACnet router serves its MS/TP segment. Include a separate line in the quote for units where the interface, router or required measurement is missing.
For a project enquiry, attach the equipment schedule, the checked point list and the trend interval needed by the operator. Identify any units that have changed since the schedule was prepared.